We completed this $2-million project within a remarkably brief 6-week period. Our teams worked 24/7 to refurbish and modify the vessel car. This turnkey project was executed during the steel mill’s annual shutdown. Delivery of this substantial component was accomplished overnight, requiring a high degree of coordination